新建铁路西安至宝鸡客运专线
锥体护坡
施工作业指导书
中铁一局西宝客专指挥部
二0一一年十二月 · 西安
目 录
1 适用范围 ························································································································· 2 2 设计概况及编制依据 ······································································································· 2 2.1 设计概况 ···································································································································· 2 2.2编制依据 ····································································································································· 2 3验收标准 ·························································································································· 2 4作业准备 ·························································································································· 2 5 技术要求 ························································································································· 3 6施工工序及工艺流程 ········································································································ 3 6.1施工流程 ····································································································································· 3 6.2施工工序 ····································································································································· 4 7施工要求 ·························································································································· 5 8劳动组织 ·························································································································· 5 9材料要求 ·························································································································· 6 10机械设备配置 ················································································································· 6 11质量控制及检验 ··························································································································· 6 12安全及环水保要求 ·········································································································· 7
- 1 -
1 适用范围
适用于西宝铁路客运专线桥台处锥体护坡施工。 2 设计概况及编制依据 2.1 设计概况
西宝铁路客运专线桥桥台锥体护坡垂裙采用C25混凝土浇筑,护坡采用35cm厚浆砌片石铺砌和预制块,下设10cm碎石垫层。 2.2编制依据
2.2.1《漆水河特大桥桥梁工程施工图》(图号:西宝客专施桥(特)01-02-01,01-02-02); 2.2.2《高速铁路路基工程施工工质量验收标准》(TB10751-2010); 2.2.3《高速铁路桥涵工程施工工质量验收标准》(TB10752-2010) ; 2.2.4《铁路混凝土工程施工质量验收标准》(TB10424-2010); 2.2.5施工调查、踏勘资料。 3验收标准
表3 砌体允许偏差和检验方法 序号 1 2 3 4 5 6 项目 顶面高程 表面平整度 坡度 厚度 底面高程 反过虑层厚度 允许偏差(mm) ±50 20 不陡于设计要求 不小于设计要求 ±50 不小于设计要求 检验方法 水准仪检查 2m靠尺检查 测量检查 尺量检查 测量检查 尺量检查
4作业准备
4.1施工前,技术人员熟悉图纸、验标、规范等相关技术要求。
4.2混凝土预制块采用在小型构件厂集中预制,运至现场集中安装。混凝土及砂浆在5#拌合站统一拌制,运至现场浇筑和砌筑。
4.3桥台锥体填土基本稳定后进行锥体坡边铺砌。
4.4坡面整修:采用挂线法将锥坡面按设计坡度刷平,坑凹不平部分填补夯实,使坡面平整圆顺,报监理工程师验收合格进行侠道工序施工。
4.5现场布置:根据现场情况确定施工便道位置及走向,砂石材料等的分类堆码场地,机具设备、拌和站的摆放位置。便道选用桥台施工便道,材料堆放场地设在锥坡坡脚5m以外,并将材料堆放场地硬化,材料堆放下垫上盖以保证施工材料不受污染。
2
4.6材料试验送检工作:砂、水泥、施工用水等原材料进场后及时取样送检,确定砂浆配合比。 5 技术要求
5.1水平砌缝宽度不大于3cm,竖向砌缝不大于4cm,填腹石的砌缝彼此错开。
5.2砌体工程所用砂浆强度等级符合设计要求。砂浆具有适当的流动性和良好的和易性。砂浆稠度按标准圆锥体在垂直方向沉入砂浆的深度表示,为40~70mm。 5.3已凝结的砂浆禁止使用。 6施工工序及工艺流程 6.1施工流程
测放锥坡平面位置 材料进场、检测 拌合砂浆 摊铺砂浆 码砌块石 砂浆勾缝、灌浆 坡率检查 图6.1-1 锥坡施工工艺流程图
基础标高复测 锥坡基础开挖 基础垫层施工 3
图6.1-2 锥坡设计大样图
6.2施工工序 6.2.1测量放样
桥台顶帽施工完成且相邻路基填筑万抽,将现场进行大致整平,采用极坐标法对桥台锥体进行准确测量,确定锥坡填筑坡脚线并撒白灰线。 6.2.2垂裙开挖
垂裙开挖前,先将基础进行准确放样,再加密圆弧段位置桩,每2m一个点,并将点位垂裙基础外边线点引出,以便于基坑开挖完,能及时恢复垂裙线,开挖时预留20cm采用人工开挖。 6.2.3垂裙浇筑
垂裙采用C25混凝土基础,施工前,先将基础底面平整,用小型机具夯实,在进行模板安装。 6.2.4坡面铺砌
坡面铺砌前先铺设10cm碎石垫层,坡面铺砌采用35cm厚浆砌片石护坡,砌筑时采用一顺一丁顺序砌筑,砌筑过程中不能出现通缝,保证在基础不均匀沉降过程中不致撕裂。 6.2.5泄水孔布置
平台以下锥体护坡设置泄水孔,次用梅花形布置,间距不大于1.5m,布置时泄水孔一
4
端贴在碎石垫层上,同时要在后面放上反虑层合成材料。以使积水顺利的留出锥体护坡。 6.2.6检查台阶砌筑
锥体检查台阶采用M10浆砌片石,台尾与人行道连接采用M10浆砌片石。 7施工要求
7.1在砌筑前每一石块均应用干净水洗净并使其彻底饱和,垫层亦应干净并湿润。所有石块均应座于新拌砂浆之上,在砂浆凝固前,所有缝应满浆,石块固定就位。垂直缝的满浆系先将已砌好的石块的侧面抹浆,然后用侧压砌置下一相邻石块;或石块就位后灌入砂浆, 填满垂直缝时,应用竹片捣实。
7.2如果石块松动或砌缝开裂,应将石块提起,将垫层砂浆与砌缝砂浆清扫干净,然后将石块重铺砌在新砂浆上。
7.3砌筑锥坡时预留30cm宽的人形通道,修整成台阶状,以利于施工中人员及材料上下。砌筑完成后再将人形通道补砌。
7.4在砂浆凝固前应将外露缝勾好,勾缝深度不小于20mm。如条件不允许时,应在砂浆未凝固前,将砌缝砂浆刮深不小于20mm,为以后勾缝作准备。
7.5砌体应分层砌筑,体积较大的石块由专人用风钻配合楔子破碎,然后两人一组将规则的块石搬运至砌筑区域,注意搬运块石时轻拿轻放,砌筑上层块石时不应振动下层,砌筑完成后24小时内不能在坡面上行走,不准在已砌好的砌体上抛掷、滚动翻转或敲击石块。 7.6锥坡坡面应平整、坡度正确,皮带缝宽度不小于2.5cm。施工过程中通过坡底、坡顶拉线控制坡面的平整度和坡度。 8劳动组织
表8.1-1 现场管理人员配置
序号 1 2 3 4 5 岗位 施工现场负责人 现场技术负责人 技术及安全质检人员 现场领工员 实验 合计 人数 1 1 2 1 2 职 责 负责现场施工总体策划、管理、协调。 对现场施工技术把关,负责现场技术管理。 负责现场具体技术、安全、质量控制工作。 协助现场负责人做好协调工作,管理工作。 负责现场具体实验工作。 7人
表8.1-2 现场劳动力配置表 序号 1 2 工 种 挖掘机司机 吊车司机 人数(人) 2 2 序号 6 7 工 种 电工 砼拌和站 人数(人) 1 3 5
3 4 5 罐车司机 装载机司机 混凝土工 2 2 10 8 9 普工 架子工 合计 8 15 45人 9材料要求
9.1砌筑用的片石单轴抗压强度应≥30Mpa。石料选用厚度不小于15cm具有一定长度和宽度的石料。
9.2石料应强韧、密实、坚固与耐久,质地适当细致,色泽均匀,无风化剥落和裂纹及结构缺陷。
9.3用作镶面石的片石应选择表面比较平整、尺寸较大的片石,其边缘厚度不得小于15cm。 10机械设备配置
按照施工计划安排要求,拟配置一下机械
表10 主要机械设备配置表
序号 1 2 3 4 5 6 7 8 9 设备名称 挖掘机 混凝土拌合站 混凝土运输罐车 汽车吊 水泵 发电机 小型夯机 吊斗 混凝土输送泵车 规格型号 PC200 2HZS120 8m QY20 100D-16X 160kw 0.5m~1m SY5293THB37 333数量 1台 1套 2台 1台 2台 1台 2台 2个 1 11质量控制及检验 11.1质量控制 11.1.1锥体护坡填土
锥体护坡填土时为了保证填土的压实度,可以采用超宽填筑,超宽部分的松土可以采用人工给予清除,但要注意表面要进行夯实,保证锥体护坡表面元顺和坚实。 11.1.2基础处的土质
基础部位是升水性土质时,基础底会在长期的渗水过程中有所下沉,为了减少下沉量可以通过加大基础底面的尺寸,从而减小沉降。
11.1.3反过滤层和碎石垫层的布置严格按照图纸设计要求进行施工。
11.1.4砌体砂浆配合比准确,各砌体的水平砌缝应大致水平;施工段内各砌缝应互相错开;砌缝砂浆必须饱满。 11.2检验
6
11.2.1原材检验:水泥按照同一厂家、同一编号、同生产日期连续进场的散装水泥按照500t为一批检验验收,不足500t时按一批验收;细骨料按照连续进场的同料源、同品种、同规格的每400m3(600t)为一批检验验收,不足时按一批验收;粗骨料按照连续进场的同料源、同品种、同规格的每400m3(600t)为一批检验验收,不足时按一批验收;砌筑所用的石材质地坚硬、石质均匀、不易风化、无裂纹。
11.2.2工序检验:在锥体护坡施工过程当中每道工序按照三检制度进行验收,层层把关。 11.2.2资料检验:每道工序完成组织验收合格后,应完成原材料的质量证明文件和抽样检验报告、工序施工记录、自检和交接检查记录、检验报告的整理和收集。 12安全及环水保要求 12.1安全要求
12.1.1未经安全教育的管理人员及施工人员不准上岗。未进行三级教育的新工人不准上岗。变换工种或参加采用新工艺、新工法、新设备及技术难度较大的工序的工人必须经过技术培训,并经考试合格者才准执证上岗。
12.1.2严禁酒后上岗,严禁疲劳上岗;进入施工现场必须戴安全帽;不准穿拖鞋、高跟鞋、裙子或赤脚、赤膊上班作业;机床作业必须戴手套、防护镜。
12.1.3禁止施工机械、车辆超坐载人以及无“特种作业人员操作证”、“驾驶证”人员驾驶施工机械、车辆。
12.1.4施工现场各种防护装置、设施和安全标志齐全。
12.1.5加强机械设备检查、维修、保养,不得带病工作,严格操作规程。 12.2环水保要求
12.2.1 配备专用洒水车,对施工现场和运输道路经常进行洒水湿润,减少扬尘。 12.2.2 合理安排施工作业时间,尽量降低夜间车辆出入频率,夜间施工不得使用噪音大的机械。
12.2.3施工营地和施工现场的生活垃圾和建筑垃圾,集中堆放,统一弃置于指定地点,不随意弃放。
12.2.4施工废水、生活污水不得直接排放。
7